Retrofitting Existing Power Systems for AI Clusters

Retrofitting Existing Power Systems for AI Clusters

Retrofitting Existing Power Systems for AI Clusters

Retrofitting Existing Power Systems for AI Clusters

Executive summary The IT industry is developing large generative AI models at a fast pace. These models can require megawatts of power at hundreds of kW/rack in data centers, known as AI factories. This paper explains the unique power requirements of these workloads and the challenges data center operators have in supporting them. Guidance is provided on how to provision existing data centers to support these loads.

Energy Management Research Center

White Paper 126 Version 1

by Victor Avelar Stuart Sheehan Allegia (Gia) Wiryawan

RATE THIS PAPER 

https://blogs.nvidia.com/blog/ai-factory/#:%7E:text=AI%20factories%20do,market%20differentiation%20tomorrow. https://www.surveymonkey.com/r/XWL97T3

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 2

Retrofitting Existing Power Systems for AI Clusters

Key takeaway 1 AI compute clusters rewrite the density rulebook: they will overwhelm legacy power paths unless retrofits account for the core challenges facing operators. Key takeaway 2 Start with a load study to understand your true power capacity and then design head room and live monitoring into your systems. Key takeaway 3 Then address the series of challenges data center operators must overcome to provision their existing data center for AI: overload, block size, arc flash, voltage, power distribution unit (PDU) limits, and variable frequency drive (VFD) harmonics. Key takeaway 4 Your solution playbook must include: Increasing distribution block size, limiting fault current, bringing in liquid cooling, addressing harmonics, and adding continu- ous monitoring. Use validated reference designs that incorporate these and other design practices. AI workloads influence data center power systems differently than traditional IT workloads. Most data center electrical infrastructure was engineered for lower rack density, some by a factor of 10x or more compared to the 100+kW racks of today. Modernizing to meet evolving requirements – in a living operating data center - is a real obstacle to leveraging the benefits of AI factories. We are still in the early stages of understanding how different AI workloads impact data center power systems. Most assume that power system challenges are limited to the pretraining and post-training (e.g., fine-tuning) of large language models (LLMs). However, within these categories, a range of variables can either increase or decrease the strain on power systems and we currently lack detailed power pro- files1 to quantify their effects.2 The rapid evolution of AI research3 makes supporting these workloads a moving target. For instance, newer, compute-intensive inference tasks-sometimes called “long thinking,”4 may also present significant power chal- lenges, but specific power profiles for these workloads are not yet available. Power profiles are essential for predicting how a data center’s power system will re- spond to specific AI workloads. While we may not have comprehensive profiles for every workload, we have identified five key attributes and trends that help us esti- mate the demands of a worst-case scenario. By designing data center power sys- tems to accommodate these worst-case profiles, we can better verify readiness for future generations of AI workloads.

1 The sum of all power drawn by a data center’s IT loads charted over time. 2 Examples of variables include precision, data batch size, model compression techniques, accelerator

(type, generation, & cooling method), and workload orchestration. 3 I.e., in-memory computation, compute-efficient algorithmic operations, algorithm evolution, and others. 4 This is also known as test-time scaling, one of three scaling laws, but others may follow.

Introduction

Key takeaways

https://www.se.com/us/en/download/document/RD108DSR0/ https://blogs.nvidia.com/blog/ai-factory/#:%7E:text=AI%20factories%20do,market%20differentiation%20tomorrow. https://blogs.nvidia.com/blog/ai-scaling-laws/#:%7E:text=Pretraining%20scaling%20is%20the%20original%20law%20of%20AI%20development.%20It%20demonstrated%20that%20by%20increasing%20training%20dataset%20size%2C%20model%20parameter%20count%20and%20computational%20resources%2C%20developers%20could%20expect%20predictable%20improvements%20in%20model%20intelligence%20and%20accuracy. https://blogs.nvidia.com/blog/ai-scaling-laws/#:%7E:text=Post%2Dtraining%20techniques,healthcare%20or%20law. https://huggingface.co/spaces/HuggingFaceH4/blogpost-scaling-test-time-compute https://www.wwt.com/article/ai-precision-the-hidden-cost-of-cutting-corners#:%7E:text=Precision%20refers%20to,and%20computer%20architecture. https://www.ultralytics.com/glossary/batch-size#:%7E:text=In%20machine%20learning,efficient%20and%20scalable. https://en.wikipedia.org/wiki/Model_compression https://www.supermicro.com/en/glossary/ai-accelerator#:%7E:text=An%20AI%20accelerator%20is,various%20industries%20and%20applications. https://www.dell.com/en-us/blog/artificial-intelligence-is-accelerating-the-need-for-liquid-cooling/#:%7E:text=The%20cooling%20challenges,demands%20are%20increasing. https://www.purestorage.com/knowledge/what-is-ai-orchestration.html#:%7E:text=AI%20orchestration%20aims,achieve%20optimal%20outcomes. https://cse.umn.edu/ece/news/new-hardware-device-make-artificial-intelligence-applications-more-energy-efficient https://arxiv.org/abs/2410.00907 https://news.mit.edu/2025/machine-learning-periodic-table-could-fuel-ai-discovery-0423 https://www.netguru.com/blog/ai-model-optimization https://blogs.nvidia.com/blog/ai-scaling-laws/

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 3

Retrofitting Existing Power Systems for AI Clusters

Every organization will need to address power system design challenges based on their unique AI workloads5 and data center requirements. In this paper, we outline the key attributes and trends shaping AI power demands, define a representative worst-case power profile, and map the resulting challenges to data center power systems. We also present retrofit strategies to help existing sites meet these new standards. Let’s talk about five key attributes and trends:

1. Accelerator network communication – Accelerators like GPUs can process data and generate tokens at a much faster rate than the communication speed between them. This makes accelerator network communication latency a bottleneck that determines how fast you can complete a given workload. A cost-effective and power-efficient approach to decrease this latency within the rack, is to use copper network cables given the short distances. However, if we used copper to connect the racks (inter-rack communication), the longer distances would introduce untenable latency. This means we need faster, more expensive, and energy-intensive, inter-rack communication (e.g. fiber). Hence the incentive to maximize the number of accelerators in a rack. This is what leads to higher rack densities in AI clusters. See “Accelerator network communication” section of White Paper 110 for more information on latency.

2. Thermal design power (TDP) of accelerators – thermal power consumption, measured in watts, is commonly specified with TDP. TDP, and the associated compute performance, trends upward with new generations of accelerators. This means you can train models and infer (both of which generate tokens) in less time and with lower cost. This trend adds to increasing rack densities.

3. Peak power – While nearly all IT workloads exhibit peak power consumption, chips used in AI workloads may exceed their TDP multiple times per second and later idle. This higher threshold is referred to as the electrical design point (EDP). These transients may exceed the steady state TDP (e.g., 50%) for tens of milliseconds while not violating the average long-term TDP thermal limits. Figure 1 illustrates an example of power peaks that exceed TDP and later fall to an idle power state. The profile, duration, and frequency of these peaks and lows will vary depending on some key variables. These include IT hardware (i.e., GPUs, power supplies, storage, and network), AI workload, and software limits imposed on loads (i.e., power limits). The magnitude of these peaks and valleys will be lower when measured at the data center level (due to other IT hardware used in an AI cluster such as network switches and storage).

0

200

400

600

800

1000

1200

0 40 80 12 0

16 0

20 0

24 0

28 0

32 0

36 0

40 0

44 0

48 0

52 0

56 0

60 0

64 0

68 0

W at

ts

Time (milliseconds)

TDP Software Control: power smoothing

Software Control: power capping

Idle power

5 AI workloads can include inference and training. Training encompasses a spectrum of techniques in- cluding pre-training (training from scratch), fine-tuning, prompt tuning, etc. The AI clusters required for these workloads may range from a data center with 100’s of megawatts of racks to several racks.

Figure 1

Example of accelerator peaks and idle states shown in millisecond timescale (green line represents TDP)

https://www.supermicro.com/en/glossary/ai-accelerator#:%7E:text=An%20AI%20accelerator%20is,various%20industries%20and%20applications. https://blogs.nvidia.com/blog/ai-tokens-explained/#:%7E:text=Tokens%20are%20tiny,learn%20and%20respond. https://www.se.com/us/en/download/document/SPD_WP110_EN/ https://www.gigabyte.com/Glossary/tdp https://developer.nvidia.com/blog/selecting-large-language-model-customization-techniques/#:%7E:text=Large%20language%20models,or%20organizational%20context.

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 4

Retrofitting Existing Power Systems for AI Clusters

4. Synchronous computation – The power consumption pattern for virtually all IT equipment and workloads resembles a series of peaks and valleys over time. This pattern for traditional IT workloads is asynchronous, meaning that the power consumption peaks occur at different times and don’t coincide (i.e., loads are diversified). For example, while individual servers may have a power variance of 60% between idle and full load, the aggregate load from all servers (as seen by a UPS) will have a lower variance. The probability that all these peaks occur at the same time is very low. This asynchronous pattern is what allows data center designers to “oversubscribe” power and cooling sys- tems like UPS and chillers. In contrast, certain AI workloads may result in a synchronized power con- sumption pattern for all AI servers. This means that peak power draw occurs at the same time multiple times per second, acting like quick step loads. Fig- ure 2 provides a hypothetical illustration of how the sum (blue line) of all the workloads varies only slightly for asynchronous workloads but for synchro- nous workloads, the sum is highly variable.

0 500

1000 1500 2000 2500 3000 3500 4000 4500 5000

0 100 200 300 400 500

Po w

er (k

W )

Time (ms)

0 500

1000 1500 2000 2500 3000 3500 4000 4500 5000

0 100 200 300 400 500

Po w

er (k

W )

Time (ms)

IT load 1 IT load 2 IT load 3 IT load 4 IT load 5 Sum

Asynchronous workloads Synchronous workloads

5. AI cluster size – certain AI workloads can be large, parallel processes that

extend beyond single servers, potentially utilizing thousands of accelerators. For example, pre-training LLMs can require a dedicated data center loaded to nearly 100%. Depending on the data center size, even a modest AI training cluster represents a significant percentage of data center load.

The type of workloads we refer to in this paper rely on scale-out computing (a large number of machines running in parallel). The AI servers are assembled into an array of racks known as an AI cluster which essentially operate as a single computer. Each compute rack in a cluster could be over 100 kW with direct-to-chip liquid- cooled servers. Traditional power distribution architectures are unable to support these densities without changes to the existing electrical system. While White Paper 110, The AI Disruption: Challenges and Guidance for Data Cen- ter Design, provides high-level recommendations to address these challenges, this paper provides more detailed guidance for those operators that are ready to imple- ment in existing data centers. Table 1 provides the challenges and their mapping to four power subsystems.6 Figure 3 illustrates the electrical flow of the subsystems (from input power to critical rack distribution) and calls out the challenge(s) associ- ated with each subsystem. For convenience, each challenge in the table is hyper- linked, so you can easily navigate to that section. Also, every page has a “home” symbol on the upper right which returns you to Table 1.

6 See White Paper 61, Electrical Distribution Equipment in Data Center Environments

Figure 2

Hypothetical comparison between asynchronous and synchronous workloads

https://www.se.com/us/en/download/document/SPD_WP110_EN/ https://www.se.com/us/en/download/document/SPD_WP110_EN/ https://www.se.com/us/en/download/document/SPD_VAVR-8W4MEX_EN/

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 5

Retrofitting Existing Power Systems for AI Clusters

Challenge

Onsite power

sources Main SG

UPS systems

Critical dist.

1 Lack of load diversity and peaky loads increase risk of overload

2 Small power distribution block sizes are impractical

3 Increased risk of arc flash hazard complicates work practices

4 120/208 V distribution is impractical to deploy

5 Standard 60/63A rack power distribution units (PDU) impractical to deploy

6 CDU pump VFD harmonics risk causing equipment malfunctions

7 * High rack temperatures increase risk of failures & hazards

Onsite power sources

Main switchgear

UPS system

Critical distribution

Challenge 1

Challenge 3

Challenge 2

Challenge 5

Challenge 4

Challenge 7

Challenge 6

These four data center subsystems are described below: • Onsite power sources – Includes power sources like generators and the as-

sociated switchgear.

• Main switchgear – Includes the main breakers that feed subsystems such as cooling, UPS, and load banks.

• UPS system – Includes, not only the UPS, but also the batteries and the UPS output switchgear, which includes the maintenance bypass.

• Critical distribution – Includes step-down transformer(s)7, distribution circuit breakers, branch breakers, and rack power distribution units (rPDU).

7 International Electrotechnical Commission (IEC) countries don’t typically use step-down transformers

in data center critical distribution.

Figure 3

A data center’s four power subsystems

Table 1

Impact of challenges on power subsystems

* Not discussed in this paper as it is thoroughly covered in White Paper 110.

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 6

Retrofitting Existing Power Systems for AI Clusters

How this challenge impacts the power system Three of the key AI attributes and trends discussed in the introduction (peak power, synchronous computation, & AI cluster size) can be combined to form a worst-case power profile. This profile increases the chance of overload and potentially reduces the life of upstream infrastructure. Note that the word “average power” related to this challenge, implies a specific time scale. (See sidebar) When you combine accelerator power peaks with synchronous computation, the re- sulting peak load on the physical infrastructure is proportional to the accelerator quantity. Fortunately, the collection of other IT components inside and outside the server dampen the magnitude of the peaks. This is where the AI cluster size attrib- ute comes in. The power profile of the AI cluster, relative to the data center’s IT de- sign capacity (kW), determines the impact on the data center’s physical infrastruc- ture. Assuming a worst-case power profile, if a 1N data center’s only load is an AI cluster, and its average load approaches the data center’s IT capacity, the data center will likely experience consistent overloads. The greater the proportion of traditional IT workloads, the less likely the data center will experience this chal- lenge. This is because the asynchronous load will dampen the effect of the synchro- nous EDP transients. Since we don’t yet have power profiles for different AI work- loads, we will assume the worst-case profile for this challenge, which does not include traditional loads. Even though the accelerator peaks are of short duration (tens of ms), they may im- pact upstream power infrastructure. If the magnitude and frequency of the peak ex- ceeds the specifications (rated current, overload specifications, and rate of change) of upstream infrastructure such as UPS and generators, their performance can be compromised. Note that the peaks may lead to two distinct and inde- pendent challenges, each with their own risk: overload and step load. It's possi- ble that equipment is sized such that it isn’t overloaded yet is unable to support the step load. Potential impacts of exceeding design limits are: Onsite power sources8 • Degrading generator power quality (frequency & voltage) below acceptable

limits for loads and UPS. Frequency and voltage regulation is especially vul- nerable to accelerator transient step loads (e.g., peak to idle states), espe- cially when heavily loaded. If these step load thresholds are breached (magni- tude & rate of change), the generator may automatically shut down to safe- guard itself and connected loads. This could happen even when the peaks do not overload the generator.

• Step changes could create oscillations or resonances with site power infra- structure such as distribution equipment.

Electrical switchgear equipment • Increased risk of tripping circuit breakers. Circuit breakers with electronic trip

units often have a thermal memory function to prevent conductors from over- heating during cyclic loading. Continuous peaks may lead a breaker to open.

• Thermal stress and aging of distribution components: insulation, wire termina- tions, and fuses.

• Nuisance tripping of protection devices.

8The Llama 3 Herd of Models, July 23, 2024, p. 14, "During training, tens of thousands of GPUs may in-

crease or decrease power consumption at the same time, for example, due to all GPUs waiting for checkpointing or collective communications to finish, or the startup or shutdown of the entire training job. When this happens, it can result in instant fluctuations of power consumption across the data cen- ter on the order of tens of megawatts, stretching the limits of the power grid. This is an ongoing chal- lenge for us as we scale training for future, even larger Llama models."

1. Lack of load diversity and peaky loads increases risk of overload

Average power The average accelerator power consumption we refer to is over a period of a few seconds, not over days or weeks. It is over this worst- case timespan that we determine how much of the data center capacity is utilized. If we were to average over a day or two, the cluster’s idle periods would lower the average, leading you to believe that the data center utilization was lower. Note that when we talk about the total data center power, the total is composed of more than the totality of accelerators. The other server components, data storage, and networking, all combine to dull the impact of the transients.

Critical dist.

UPS systems

Main SG

Onsite power

sources

https://www.productinfo.schneider-electric.com/micrologicbuserguide/doca0216-mtz-micrologic-b-user-guide/English/DOCA0216_MicroLogicB_User_Guide_0000630824.xml/$/MicB_Thermal_Memory_0000637128#:%7E:text=The%20thermal%20memory,the%20protection%20settings https://digital-library.theiet.org/doi/10.1049/ip-smt%3A19970861 https://ai.meta.com/research/publications/the-llama-3-herd-of-models/

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 7

Retrofitting Existing Power Systems for AI Clusters

Uninterrupted power supply (UPS) system • Switches to bypass if inverter limits (instantaneous & thermal) are exceeded.

• Draws energy from battery if UPS AC input current limits are exceeded.

• Degrades battery state of charge (SOC) if overloads are significant enough to draw from battery and frequent enough to not allow full battery recharge be- tween peaks.

• Shortens life of batteries (i.e., reduced state of health) through cycling and thermal wear (i.e., increased temperatures).

• Decreases life of semi-conductors and fuses if design limits are exceeded.

How to address this challenge in existing data centers To address this challenge, we assume that your data center has enough spare capacity to support the average AI cluster load.9 The optimal solution to this chal- lenge depends on several factors related to the AI workload power profile and the electrical distribution topology. Prior to adding the AI cluster, the first step is to per- form a detailed load study for the upstream infrastructure. This should include:

1. Anticipated AI load – Estimate the expected frequency and magnitude of any power peaks. While not foolproof, the nameplate power rating (watts) of IT power supplies can be more indicative of the AI load’s AC power peaks than TDP. This can be a useful conservative estimate if the server manufacturer data does not specify peak values. Note that power supply capacitance helps “absorb” power peaks; more capacitance will better limit power peaks. This capacitance varies among different IT power supplies. Other loads like storage and networking will dilute the magnitude of a peak (lower peak to av- erage). Remember to account for the power required to cool the AI cluster.

2. Available electrical capacity – Use power quality meters10 to monitor the power draw on the main breaker over the course of a week to determine the data center’s average and peak load. Document the nameplate capacity and available capacity of components that will supply the AI cluster including transformers, circuit breakers, generators, and UPSs. Verify that the power infrastructure's redundancy meets the original design specifications (e.g., standby generators, UPS, PDUs, etc.).

With the details from the load study, you can take a more informed design ap- proach. We recommend the following solutions listed in order of most feasible for a production data center. • Size the AI cluster to match the spare data center capacity – This solution

addresses overloads. The least disruptive solution for a production data cen- ter is to decrease the number of proposed AI servers and supporting IT gear such that the resulting peak power is equal to or less than the spare capacity. This solution represents a conservative approach and should be evaluated in light of business goals. This solution does not require changes to your current facilities operation (e.g., maintenance schedules, generator testing, etc.).

• Accelerator software control – Using software to cap accelerator power con- sumption may allow your proposed AI cluster to operate within your data cen- ter’s spare capacity (addresses overloads). This necessarily means a tradeoff between performance and energy consumption dependent on the extent of

9 The spare capacity of the main switchgear and UPS is greater than or equal to the anticipated AI clus-

ter’s average load (including cooling load). 10 Unlike other meters, power quality meters are able to capture sub-cycle wave forms.

https://docs.nvidia.com/dgx/dgxh100-user-guide/power-capping.html

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 8

Retrofitting Existing Power Systems for AI Clusters

the capping.11 Accelerator power smoothing software addresses step loads by injecting ex- tra load, thereby increasing the idle power. Raising the idle power decreases the step load seen by the electrical infrastructure. This reduces the negative impact of rapid step loads such as with generators.

• Install a specialized energy storage system – This solution addresses both overloads and step loads. Examples of energy storage include high-cycle bat- teries and super capacitors. For overloads, the stored energy discharges dur- ing the peaks, acting like a peak shaver such that the upstream systems do not see the peaks. For step loads, energy storage charges during the idle points to decrease the step load, acting like a shock absorber such that the upstream systems see a smoother load. In both cases, the controls determine when to charge and discharge thereby providing power smoothing.

• Use existing UPS for power smoothing – This solution addresses step loads only. If pressed to address step loads, your existing UPS may be capable of performing a power smoothing function but requires investment. Existing bat- teries must be replaced with high-cycle batteries or super caps. The UPS con- trols would also need to be altered to perform this function.

• Increase capacity of switchgear, conductors, and UPS – This solution ad- dresses overloads. The most disruptive action is to increase the capacity of the power system in a production data center. In essence, this means rightsiz- ing only the power system to accommodate the workload’s peaks. Assuming the power system is sized to the average AI cluster load, increasing the power system capacity by 6% to 15% represents about 1% to 2.5% of the total cost of the IT kit.12 It’s a small price to pay for peace of mind. Note that in this ex- ample, your data center is still rated for its original capacity because the cool- ing system capacity didn’t change. Only the power system capacity in- creases.

In all of these solutions, we recommend, at a minimum, power quality metering at the main breaker and the sub-feed breakers feeding the cluster. Also, across all de- signs, we recommend electrical power monitoring software (EPMS). EPMS polls the meters for the data. Data center operators can then monitor the power using the EPMS user interface or the EPMS can share the data with other software such as data center infrastructure management (DCIM) and building management system (BMS) software. Among other things, monitoring software allows you to set thresh- old alerts when critical levels are approached. This will allow IT admins time to as- sess which loads to temporarily throttle to avoid exceeding infrastructure limits. The risks of allowing infrastructure to “absorb” the peaks (overloading) You may be familiar with the idea of maximizing the power system’s capacity such that the EDP peaks overload system components like UPS. The typical rationale for this approach is that you can maximize the AI workload with every available watt. On the surface this sounds like a great idea, if we ignore the stress placed on the power system. Consider the perspective of a data center operator who invests mil- lions of dollars in an AI cluster to accelerate workloads (e.g., parallelization, high- speed interconnects, mixed precision, etc.). It becomes illogical, then, to jeopard- ize the very goals operators seek to achieve by knowingly overloading the underly- ing physical infrastructure. Physical infrastructure, such as circuit breakers and UPS systems, is designed and tested to withstand intermittent power transients above its rated capacity. However,

11 Zhao, et al., Sustainable Supercomputing for AI: GPU Power Capping at HPC Scale, Oct 2023, Pro-

ceedings of the 2023 ACM Symposium on Cloud Computing 12 See Appendix for assumptions.

https://arxiv.org/pdf/2402.18593v1

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 9

Retrofitting Existing Power Systems for AI Clusters

the frequency of EDP power transients significantly surpasses the typical test con- ditions for these systems. Focusing specifically on UPS. Most, if not all, three-phase UPS can support overloads to varying degrees based on their magnitude and dura- tion. However, they weren’t designed to support repetitive overloads (multiple times per second) over weeks and months. A specialized energy storage system, men- tioned above, is the appropriate solution to absorb EDP peaks. It’s difficult to pre- dict the long-term impact these overloads will have on power equipment. It’s likely that the probability of failure will increase over time compared to the same equipment operating at the rated capacity. For data centers with power system redundancy (e.g., 2N, N+1) designed into its switchgear, UPS, and generator, it may be tempting to use this redundancy as in- creased capacity. We do not recommend this practice as it comes with inherent downtime risks and requires changes to your current facility operations when your data center loses redundancy. For example, AI training would be stopped for scheduled UPS maintenance and during other degraded states (e.g., equipment failure). Also, production would cease while operating on generator because idle- to-EDP “step loads” may degrade voltage and frequency output, or worst case, cause generator shut down. Given that these AI clusters are an emerging application, we recommend engaging equipment vendors regarding your application and specific power profile. Stand- ards for addressing this challenge will develop as the industry matures. We also an- ticipate that accelerator vendors will provide more software control over these power profiles, specify additional capacitance in server power supplies, and make design changes to future accelerator generations. How this challenge impacts the power system The accelerator network communication attribute discussed in the introduction im- plies that rack densities will continue to increase well beyond 100 kW per rack. Power distribution units (PDU) and remote power panels (RPP) are typically rated for about 300 kW. This means that each PDU or RPP could support three 100 kW racks. This is impractical because the smaller the capacities, the more units must be maintained. This also wastes space, not only with the footprint of each unit, but the service clearances required. As distribution block size decreases, both infra- structure space consumption and maintenance expenses increase. This challenge is exacerbated by redundant distribution configurations. How to address this challenge in existing data centers PDU, RPP, or feeder circuit breaker capacity ratings (block size) should increase to accommodate increasing rack densities. However, increasing capacities isn’t as simple as increasing the breaker amperage. Design preferences and constraints tend to dictate the maximum distribution block size. A key constraint is the design of your data center’s existing power system. Some others include: • Increasing distribution capacities also increases fault current (discussed in

the next challenge).

• In N+1 redundancy schemes, as distribution capacities increase, stranded power increases (the “+1” is stranded). Stranded capacity decreases with in- creasing “N” (2+1, 3+1, etc.) but power distribution complexity increases.

• The need for a symmetrical layout of compute and support racks (each with their own rack density) makes it challenging to maximize the capacity utiliza- tion of both feeders and rack PDUs.

2. Small power distribution block sizes are impractical

Critical dist.

UPS systems

Main SG

Onsite power

sources

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 10

Retrofitting Existing Power Systems for AI Clusters

• Standard, off-the-shelf, ratings for equipment like busway and rack PDUs are limited. This challenges designers to achieve goals related to cost, power effi- ciency, redundancy, space utilization, etc. On the other hand, the more stand- ardization, the less opportunity for unique failures.

Given the unique characteristics of existing power systems, engage with your phys- ical infrastructure and IT vendor(s) for advice on how to adapt to your proposed AI cluster. Validated AI cluster reference designs may also provide some ideas. For example, Reference Design 108, 7392 kW, Tier III, IEC, Chilled Water, Liquid- Cooled AI Clusters, uses 100% rated 800A breakers, providing 575 kW. Reference designs also account for electric code rules when increasing the capacity of exist- ing systems.

How this challenge impacts the power system This challenge arises mainly through increasing the transformer capacity as pro- posed in the previous challenge. Unfortunately, the higher the transformer capacity, the lower the impedance to fault current. This means that if there were a fault down- stream of the transformer, more fault current would flow with a higher-capacity transformer compared to a lower-capacity transformer. This is important because fault currents beyond 10 kiloamps (kA) at the rack may pose work restrictions for IT admins. In regions like Europe that don’t use PDU transformers, this challenge arises mainly as a result of higher capacity circuits (larger cables).

How to address this challenge in existing data centers White Paper 194, Arc Flash Considerations for Data Center IT Space, states: “The term “arc flash” describes what happens when electrical short circuit current flows through the air. A fault (the common term for short circuit) usually occurs between a live conductor (e.g., wire, bus) and another live conductor(s) or grounded metal. In many cases, a single-phase fault quickly evolves into a three-phase fault. In an arc flash, the current literally travels through the air from one point to the other, releas- ing a large amount of energy, known as incident energy, in less than a second. This energy is released in the form of heat, sound, light, and explosive pressure - all of which can cause harm. Some specific injuries can include burns, blindness, electric shock, hearing loss, and fractures.”

The two most important factors13 that determine the amount of incident energy (measured in calories/cm2) are:

• Available fault current – measured in kiloamps (kA), is the maximum amount of current available (at the location of a fault) to “feed” a fault and is dependent on the electrical system design.

• Arc duration – measured in milliseconds (ms), is the amount of time it takes for a fuse or circuit breaker to open and clear a fault.

A data center’s electrical design controls both factors. A short circuit analysis deter- mines how much fault current is available at the rack PDU input. This fault current should typically be limited to 10,000 amps (10 kA) or less. If the fault current is greater than 10 kA at the rack PDU cord cap (i.e., connector), implement one or a combination of the following solutions (listed below in order of most preferred to least preferred). Consult with your physical infrastructure vendor as some cord caps or distribution equipment may have ratings greater than 10 kA.

13 White Paper 194, Arc Flash Considerations for Data Center IT Space, p. 2

3. Increased risk of arc flash hazard complicates work practices

Critical dist.

UPS systems

Main SG

Onsite power

sources

https://www.se.com/us/en/download/document/RD108DSR0/ https://www.se.com/us/en/download/document/RD108DSR0/ https://www.se.com/us/en/download/document/SPD_VAVR-6KGRYW_EN/ https://www.se.com/us/en/download/document/SPD_VAVR-6KGRYW_EN/

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 11

Retrofitting Existing Power Systems for AI Clusters

• PDU transformer impedance – transformers should be specified with 5-9% impedance to help limit fault current at the rack. Increasing impedance must be balanced with the resultant voltage drop. Though atypical in IEC coun- tries,14 PDU transformers are an effective means for limiting fault current.

• Current-limiting breaker – these breakers usually protect a group of branch breakers, and each branch breaker protects a rack PDU. If a fault occurs at the rack PDU, the main breaker limits the fault current seen by the branch breaker. It does this by partially opening its contacts thereby causing an arc which increases the impedance, limiting the amount of fault current it lets through.15 If the branch breaker doesn’t open, the main breaker ultimately will.

When pairs of breakers are “series rated”, current-limiting breakers are usually used. The breaker pair is tested together despite the downstream breaker having a lower fault current rating than what is present on that circuit. Further- more, when used with a current-limiting upstream breaker, series rating may provide selectivity which means that the branch breaker trips before the main breaker. Note that this solution mostly applies for branch breakers rated for 63 amps or less.

• Conductor length – the longer a circuit’s electrical wires (i.e., conductors) the more impedance and therefore the lower the fault current available at the end of the circuit. Sometimes increasing the length of circuits, beyond what’s re- quired, provides just enough impedance to meet a specification.

• Short-circuit current limiter block – these devices limit current similar to cur- rent-limiting breakers except that they are connected to the circuit breaker.

• Line reactor – these devices add impedance to a circuit much like transform- ers do. They are made of wire wound around a metal core and are sometimes referred to as a choke since it resists the flow of fast changes in current.

• Redundant current-limiting breakers upstream of the branch breaker – placing two current-limiting breakers in series complicates selectivity but re- duces the fault current seen by the branch breaker.

• Fuse – in general fuses interrupt fault current faster than circuit breakers given the same voltage and current rating. However, in data center applications, fuses are generally a last resort since they must be replaced after a fault, in- creasing mean time to repair. A supply of spare fuses must also be available.

How this challenge impacts the power system This challenge applies only to data centers in non-IEC countries that use PDU trans- formers to distribute 120 volts (single-phase) and 208 volts (three-phase) in data centers. The lower the voltage, the more current you need for the same power. Con- sequently, the wire must be larger to provide greater current. At 120/208 V, it would take five 60-amp circuits to power an 80 kW rack (each circuit equals 120 V x 3 phases x 60 A x 80% derating = 17.3 kW) at 1N redundancy. Most racks can ac- commodate 6 vertical rack PDUs with a rack extension kit (Figure 4) using left and right rack channels. Therefore, 5 circuits per rack is feasible at 1N but not at 2N.

A PDU transformer is not typically used in countries with 230V distribution. This is because the data center input voltage (230V) is already compatible with IT equip- ment. The data center input voltage in most North American (NAM) data centers is 277V which is too high for most IT equipment. This is why PDU transformers are re- quired to step down 277V to usable IT voltage.

14 The International Electrotechnical Commission oversees the standards for electrical equipment. 15 Discrimination, cascading, and enhanced discrimination by cascading

4. 120/208 V distribution is impractical to deploy

Critical dist.

UPS systems

Main SG

Onsite power

sources

https://www.se.com/ae/en/faqs/FA289962/

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 12

Retrofitting Existing Power Systems for AI Clusters

How to address this challenge in existing data centers Replace 120/208V PDUs with 240/415V PDUs. This simplifies the distribution (less circuits needed) and allows more space for network cable trays. As suggested in the previous “arc flash” challenges, increasing the PDU transformer % impedance will help limit the amount of fault current at the IT rack. How this challenge impacts the power system Space in AI racks is limited due to deeper servers and network cable density. Space becomes even more constrained with liquid-cooled servers because the liq- uid manifold occupies one side of the accessory channel in the rear of the rack. In this case, a typical rack can accommodate a maximum of two rack PDUs. At 230 V 63 A (IEC) and 240 V 60 A (non-IEC), the highest-capacity standard rack PDUs provide 43.6 kW or 34.5 kW respectively. Two rack PDUs will support rack densities up 87.2 kW or 69.0 kW. This is still not enough for rack densities over 100 kW and doesn’t account for redundant power paths. How to address this challenge in existing data centers While not a standard offering for all vendors, there are higher rated rack PDUs available. For example, 240 V 125 A (non-IEC) rPDU provides 71.9 kW. Using two of these can support 143.8 kW. For rack densities greater than 143.8 kW, it may be possible to add a third rPDU if the rack vendor offers a 1400 mm deep rack, or a rack extension kit. See yellow highlight in Figure 4. This will allow up to three rack PDUs at 1N or 6 rack PDUs at 2N or N+1 redundancy if both rack channels are available. For higher rack densities and redundancy options, we recommend speci- fying custom rack PDUs, as shown in Table 2. Note that IEC capacities in Table 2 may be lower with busway distribution, due to the circuit breaker’s thermal derating within tap-off boxes.

Non-IEC 40 A 60 A 100 A 125 A 150 A 175 A

240/415 V 23.0 kW 34.5 kW 57.5 kW 71.9 kW 86.3 kW 100.6 kW

IEC 32 A 63 A 125 A 150 A 160 A

230/400 V 22.2 kW 43.6 kW 86.6 kW 103.9 kW 110.9 kW

Standard Custom

5. Standard 60/63A rack PDU impractical to deploy

Figure 4

Rack extension kits provide space for an additional rack PDU

Table 2

Usable 3-phase power density per rPDU based on circuit breaker amp rating and voltage (line-to-neutral)

Critical dist.

UPS systems

Main SG

Onsite power

sources

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 13

Retrofitting Existing Power Systems for AI Clusters

Another possible solution to increase the number of feeds to the rack is to use Open Compute Project (OCP) racks. These racks have integrated power supply shelves and power busbars that distribute power to rack-mounted OCP-type IT equipment. In essence, the power shelves save space inside the rack by consoli- dating the individual power supply units (PSU) in each server. Since this architecture integrates the power distribution into the rack, it doesn’t re- quire traditional rack PDUs. Instead, the power whip from the branch breaker feeds the connector at the bottom or top of the OCP rack using an IEC or NEMA con- nector as illustrated in Figure 5. This distribution approach alleviates a significant amount of space in the rack’s accessory channel. The power shelves also allow multiple power redundancy options (e.g., N+1, N+2, 2N, etc.).

How this challenge impacts the power system Harmonics are not new to data centers and their negative consequences have largely been kept in check over the last few decades through the adoption of power factor corrected (PFC) power supplies. However, there have been a few recent in- stances where the deployment of coolant distribution units (CDU) has coincided with an increase in equipment malfunction. The thermal design power (TDP) of some chips necessitates direct-to-chip liquid cooling. The water in these systems is supplied with CDUs that may include pumps with a variable frequency drive (VFD). These drives may generate harmonics. Har- monics could negatively affect electrical devices such as air conditioning compres- sors. Harmonics can alter the shape of the voltage and current sine wave supplied to other equipment. Depending on the equipment and the severity of the distortion, the equipment may malfunction. How to address this challenge in existing data centers Considering the recent emergence of this problem, it merits further study to better understand the root cause. In the meantime, we provide the following guidance. First, given the cooling criticality of CDU pumps, they must be placed on critical UPS power in case of a power outage. Your data center’s existing UPS system may not have spare capacity for the additional pump load. Therefore, install a separate UPS system to support CDU pumps. Verify that the UPS can support the pump in- rush current. Alternatively, you may specify pumps with frequency converters that avoid high inrush current, sometimes referred to as “soft start”. Second, any harmonics generated by drives may be addressed by specifying a voltage and frequency independent (VFI) UPS. Alternatively, active filters (Figure 6) are capable of addressing a wide range of harmonics. For more information on this topic, see White Paper 510, Impacts of Variable Speed Drives on a Building's Power Quality.

6. CDU pump VFD harmonics risk causing equipment malfunctions

Critical dist.

UPS systems

Main SG

Onsite power

sources

Figure 5

OCP Open Rack V3 power distribution to integrated power shelf Source: Open Rack V3 Meta High Power AC Whip Power Cable specification

https://www.opencompute.org/documents/open-rack-v3-bbu-shelf-spec-rev1-1-pdf-1#:%7E:text=The%20Open%20Rack%20Power%20Architecture,DC%2DDC%20charger/discharger. https://www.se.com/us/en/download/document/SPD_SADE-5TNM3Y_EN/ https://www.se.com/us/en/download/document/Buildings_WP510_EN/? https://www.se.com/us/en/download/document/Buildings_WP510_EN/? https://drive.google.com/file/d/1fASxoGqHqn9cqjocB9hr8ZGHvPdYhr5V/view https://drive.google.com/file/d/1fASxoGqHqn9cqjocB9hr8ZGHvPdYhr5V/view https://drive.google.com/file/d/1fASxoGqHqn9cqjocB9hr8ZGHvPdYhr5V/view

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 14

Retrofitting Existing Power Systems for AI Clusters

For organizations that will deploy AI workloads in a colocation or an existing on- prem data center, there are power infrastructure challenges they must overcome. The following next steps will help address these challenges: Leverage validated reference designs. These tools incorporate the latest knowledge from both IT and physical infrastructure vendors. They should include a set of engineering documents such as electrical one-line diagrams, piping dia- grams, floor plans, and equipment lists. Perform a load study. Prior to adding the AI cluster, perform a load study for the up-stream infrastructure. This should include a detailed assessment of the antici- pated AI load profile and the available electrical capacity. Determine if the power peaks from the new AI cluster will overload your power system. If an AI cluster’s average power consumption approaches a data center’s IT capacity, the data center will likely experience consistent overloads. If this is the case, review the list of solutions most feasible for your data center. Use power quality metering and monitoring software. This will allow you to moni- tor critical infrastructure loads and set threshold alerts when critical levels are ap- proached. For example, IT admins will have time to assess which loads to tempo- rarily throttle to avoid exceeding infrastructure thresholds. Add PDU transformers to distribute power to the AI cluster. Though mainly used in North American data centers, PDU transformers are an effective fault current lim- iter for any region. Higher-capacity isolation transformers will support more racks compared to traditional PDUs. The increased fault current from larger capacity transformers will need to be counterbalanced with available fault current mitigation solutions listed in this paper. Performing a short-circuit analysis determines how much fault current is available at the rack PDU input. This fault current should typi- cally be limited to 10,000 amps (10 kA) or less. Implement the highest-capacity rack PDUs available for your region. AI racks can easily reach over 100 kW with the latest accelerator-based servers. Most racks have space for 2 rack PDUs at 1N redundancy. 1400 mm deep racks or racks with an optional extension kit, will allow up to three rack PDUs at 1N or 6 rack PDUs at 2N or N+1 redundancy, if both rack channels are available. If unable to support the required rack kW and redundancy with standard rack PDUs, consider higher-ca- pacity custom rack PDUs. Specify a UPS that can mitigate the harmonics from variable speed coolant dis- tribution unit (CDU) pumps. If your AI servers are liquid-cooled, they will require a CDU to distribute coolant to the server’s components. These variable speed pumps create harmonics that may interfere with other equipment. Placing these pumps on a UPS will mitigate these harmonics and maintain cooling during a power outage.

Next steps

Figure 6

Examples of active harmonic filters

https://www.se.com/us/en/work/solutions/data-centers-and-networks/reference-designs/

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 15

Retrofitting Existing Power Systems for AI Clusters

About the authors

Victor Avelar is a seasoned expert in data center energy efficiency and design, serving as the Chief Research Analyst at Schneider Electric’s Data Center Research & Strategy team. With over 25 years of experience, Victor leads cutting-edge research and best practice development for sustainability, risk management, and next-generation data center technologies. He’s a trusted advisor to clients globally, providing actionable insights on enhancing infrastructure performance through innovative solutions such as liquid cooling and energy modeling. Known for his clear, practical guidance, Victor helps organizations tackle the evolving challenges of sustainable and efficient data center operations. He is central to the development of technology adoption forecasts for data centers. He also leads the peer review process for all DCRS content. Victor holds a bachelor’s degree in mechanical engineering from Rensselaer Polytechnic Institute and an MBA from Babson College. He is a member of AFCOM and a sought-after speaker on AI infrastructure. Stuart Sheehan is a Lead Systems Engineer at Schneider Electric. He works to explore new technologies and incubate new solutions and architecture for the data center, focusing on the increasing union of sustainability, digitization, and power system and energy storage innovation. Stuart holds a Master’s degree in Mechanical Engineering from Duke University and a Bachelor’s degree in Phys- ics from Bowdoin College. Allegia (Gia) Wiryawan is a Senior Systems Design Engineer at Schneider Electric, where she plays a critical role in advancing solutions for data centers. Gia specializes in evaluating and analyzing emerging trends and technologies, focusing on power system architectures and energy storage. Her work includes developing reference design packages that integrate thought leadership and showcase our latest innovations, providing actionable strategies for optimizing data center operations. Gia’s expertise is demonstrated by practical and forward-thinking solutions for customers. Her contributions align with Schneider's commitment to sustainable and efficient energy management. She holds a Bachelor’s degree in Electrical Engineering with a minor in Com- puter Science from Tufts University. With a strong foundation in technical knowledge and analytical capabilities, she drives progress in the design and implementation of advanced data center technologies.

This document is to be considered as an opinion paper presenting general and non-binding information on a particular subject. The analysis, hypothesis and conclusions presented therein are provided as is with all faults and without any representation or warranty of any kind or nature either express, implied or otherwise.

RATE THIS PAPER 

https://www.surveymonkey.com/r/XWL97T3

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 16

Retrofitting Existing Power Systems for AI Clusters

The Different Types of UPS Systems White Paper 1

The AI Disruption: Challenges and Guidance for Data Center Design White Paper 110

Arc Flash Considerations for Data Center IT Space White Paper 194

Impacts of Variable Speed Drives on a Building's Power Quality White Paper 510

7392 kW, Tier III, IEC, Chilled Water, Liquid-Cooled AI Clusters Reference Design 108

Note: Internet links can become obsolete over time. The referenced links were available at the time this paper was written but may no longer be available now.

Contact us For feedback and comments about the content of this white paper:

Schneider Electric Data Center Research & Strategy dcsc@schneider-electric.com

If you are a customer and have questions specific to your data center project:

Contact your Schneider Electric representative at www.apc.com/support/contact/index.cfm

Browse all white papers whitepapers.apc.com

tools.apc.com

Browse all TradeOff Tools™

Resources

© 20

25 S

ch ne

ide r E

lec tri

c. Al

l ri gh

ts re

se rve

d.

https://www.se.com/us/en/download/document/SPD_SADE-5TNM3Y_EN/ https://www.se.com/us/en/download/document/SPD_WP110_EN/ https://www.se.com/us/en/download/document/SPD_VAVR-6KGRYW_EN/ https://www.se.com/us/en/download/document/Buildings_WP510_EN/? https://www.se.com/us/en/download/document/RD108DSR0/ https://whitepapers.apc.com/ https://whitepapers.apc.com/ https://tools.apc.com/ https://tools.apc.com/

Schneider Electric – Data Center Research & Strategy White Paper 126 Version 1 17

Retrofitting Existing Power Systems for AI Clusters

Rightsizing to EDP peak, costs 1% to 2.5% of the AI cluster’s (IT) capital cost This analysis estimates the cost to increase a power system’s capacity to match an AI cluster’s peak power (i.e., EDP). We assumed two different UPS design factors (1.1 and 1.2). Power system designs are typically based on “per unit” (PU) sizing factors. For example, UPSs are typically sized to 1.2 times the full IT load. We pre- sent the incremental costs as a percentage of the AI cluster’s IT cost. Assumptions: • $25 million per MW or $25/Watt is the capital cost of an AI data center includ-

ing the physical infrastructure and AI cluster.16 Assume this cost is per MW of rated IT capacity and an N+1 power system.

• $6.30/W is the estimated data center physical infrastructure capital cost at N+1 power redundancy as shown in Figure A1. Based on the Data Center Capital Cost Calculator.

• $18.70/W ($25.00 - $6.30) is the cost of only the IT (i.e., AI cluster), the total cost minus the data center physical infrastructure cost.

• 6% and 15% increase in data center power system capacity. This is the amount of extra power capacity the power system needs to support the EDP peaks at 1N redundancy. These values were estimated from an energy model that accounted for wire losses (99% efficiency) and PDU losses (varying effi- ciency). The 6% and 15% were derived from a UPS PU value of 1.2 and 1.1 respectively.

Findings: • The capex premium of increasing the power system capacity by 6% and 15%

is $0.18/W and $0.46/W respectively. This equates to 1% to 2.5% of the IT capex.

16 Stephen Lacey, Microsoft plans $80B for data centers as power constraints loom, Latitude Media,

1/6/2026

Appendix

Figure A1

Data Center Capital Cost Calculator with estimated data center capital cost for N+1 power system

https://www.se.com/ww/en/work/solutions/system/s1/data-center-and-network-systems/trade-off-tools/data-center-capital-cost-calculator/ https://www.se.com/ww/en/work/solutions/system/s1/data-center-and-network-systems/trade-off-tools/data-center-capital-cost-calculator/ https://www.latitudemedia.com/news/microsoft-plans-80b-for-data-centers-as-power-constraints-loom/#:%7E:text=%E2%80%9CThe%20cost%20of%20a%20data,on%20Latitude%20Media's%20Catalyst%20podcast.


Item Type: pdf